An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials…

The correct answer is B. Set the planning horizon in Customizing using the plant parameter settings and assign variant entries via. See the full explanation below for the reasoning.

Question

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon. What procedure do you recommend for setting the planning horizon?

Options

  • ASet the planning horizon in the MRP groups in Customizing and assign variant entries via the plant
  • BSet the planning horizon in Customizing using the plant parameter settings and assign variant entries via
  • CSet the planning horizon in the MRP groups in Customizing and store the variant values in the material
  • DSet the planning horizon in the plant parameters in Customizing and store variant entries in the material

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    76% (29)
  • C
    5% (2)
  • D
    16% (6)