C_TS4CO_1909 · Question #146
Your customer defined one distribution cycle in SAP S/4HANA. You need to define a new distribution cycle. How can you ensure the new cycle is executed only after the existing one is completed?
The correct answer is A. Assign both cycles to the same cycle run group. See the full explanation below for the reasoning.
Question
Your customer defined one distribution cycle in SAP S/4HANA. You need to define a new distribution cycle. How can you ensure the new cycle is executed only after the existing one is completed?
Options
- AAssign both cycles to the same cycle run group
- BSelect iteration in the cycle header of the new cycle
- CAssign each cycle to a different cycle run group
- DSelect iteration in the cycle header of both cycles
How the community answered
(16 responses)- A75% (12)
- B6% (1)
- C6% (1)
- D13% (2)