C_TS4CO_1909 · Question #145
You want to settle primary cost elements and secondary cost elements to different receivers. What do you use?
The correct answer is D. Source structure. See the full explanation below for the reasoning.
Question
You want to settle primary cost elements and secondary cost elements to different receivers. What do you use?
Options
- AAllocation structure
- BPA transfer structure
- COverhead structure
- DSource structure
How the community answered
(41 responses)- A7% (3)
- B15% (6)
- C5% (2)
- D73% (30)