C_TS4CO_1909 · Question #140
Plan revenu = 3000 Plan costs = 2000 Actual revenue = 1200 Actual costs = 1000
The correct answer is B. Revenue = 1200; Cost of sales = 800; WIP = 200. See the full explanation below for the reasoning.
Question
Plan revenu = 3000 Plan costs = 2000 Actual revenue = 1200 Actual costs = 1000
Options
- ARevenue = 1200; Cost of sales = 800; Reserve = 200
- BRevenue = 1200; Cost of sales = 800; WIP = 200
- CRevenue = 1200; Cost of sales = 1000; Reserve = 200
- DRevenue = 1200; Cost of sales = 1000; WIP = 200
How the community answered
(56 responses)- A4% (2)
- B75% (42)
- C5% (3)
- D16% (9)