You use a production order with product Cost by period and you entered a result analysis key and variance key. How does the system calculate variances in product Cost by Period ?

The correct answer is C. Variances = Actual costs - Delivery value - WIP. See the full explanation below for the reasoning.

Question

You use a production order with product Cost by period and you entered a result analysis key and variance key. How does the system calculate variances in product Cost by Period ?

Options

  • AVariances = Target costs - Delivery value
  • BVariances = Actual costs - Delivery value
  • CVariances = Actual costs - Delivery value - WIP
  • DVariances = Target costs - Delivery value - WIP

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    17% (6)
  • C
    72% (26)
  • D
    8% (3)