In which type of outline agreement would you see details of confirmed material quantities and delivery dates?
The correct answer is B. Scheduling agreement. A Scheduling Agreement (B) is the only outline agreement type that contains delivery schedule lines - specific confirmed quantities tied to exact delivery dates, making it ideal for JIT (Just-in-Time) supply arrangements with vendors. Why the others are wrong: A…
Question
In which type of outline agreement would you see details of confirmed material quantities and delivery dates?
Options
- AMaterial-related value contract
- BScheduling agreement
- CGeneral value contract
- DQuantity contract
How the community answered
(49 responses)- A6% (3)
- B90% (44)
- C2% (1)
- D2% (1)
Explanation
A Scheduling Agreement (B) is the only outline agreement type that contains delivery schedule lines - specific confirmed quantities tied to exact delivery dates, making it ideal for JIT (Just-in-Time) supply arrangements with vendors.
Why the others are wrong:
- A (Material-related value contract): Defines a total spend value for specific materials, but has no delivery dates or quantity confirmations.
- C (General value contract): Sets an overall spending limit across a range of materials/services - no line-item schedule or confirmed quantities.
- D (Quantity contract): Specifies a total quantity to be purchased over time, but release orders (not schedule lines) are used to call off deliveries - no confirmed delivery dates are stored within the agreement itself.
Memory tip: Think of a schedule as a calendar - the word itself tells you it tracks when things arrive. Only a Scheduling Agreement has an actual delivery schedule baked in.