How can you manage which materials can be released for a value contract? Note: There are 2 correct answers to this question.
The correct answer is C. Assign an assortment module to the value contract. D. Assign a product hierarchy to the value contract. In SAP SD value contracts, you control which materials a customer can release (order against) by assigning an assortment module (C), which is a predefined list of valid materials, or by assigning a product hierarchy (D), which restricts releases to materials within that…
Question
How can you manage which materials can be released for a value contract? Note: There are 2 correct answers to this question.
Options
- ASet up the dependent profitability segment for the value contract.
- BAssign a sales item proposal to the value contract.
- CAssign an assortment module to the value contract.
- DAssign a product hierarchy to the value contract.
How the community answered
(63 responses)- A8% (5)
- B14% (9)
- C78% (49)
Explanation
In SAP SD value contracts, you control which materials a customer can release (order against) by assigning an assortment module (C), which is a predefined list of valid materials, or by assigning a product hierarchy (D), which restricts releases to materials within that hierarchy node - both are standard mechanisms for material-level restriction on value contracts.
Why A is wrong: Dependent profitability segments relate to CO-PA account assignment for profitability analysis, not to controlling which materials are releasable from a contract.
Why B is wrong: A sales item proposal (a list of frequently ordered items) can suggest materials during order entry, but it doesn't control or restrict which materials are permitted in a value contract release - it's advisory, not restrictive.
Memory tip: Think "what limits the scope of a contract?" - Assortment modules define exactly which items are in scope (an explicit list), and product hierarchies define which category is in scope (a tree-based filter). Both are about scope restriction, which is the core job of material control on a value contract.