C_TS452_2021 · Question #81
You create a contract item for a material group. You want to prevent certain materials that belong to this material group from being ordered with reference to this contract item. How can you ensure…
The correct answer is A. Create material-specific source lists for the contract item and set the Exclusion indicator. See the full explanation below for the reasoning.
Question
You create a contract item for a material group. You want to prevent certain materials that belong to this material group from being ordered with reference to this contract item. How can you ensure this?
Options
- ACreate material-specific source lists for the contract item and set the Exclusion indicator.
- BCreate material-specific source lists outside the validity period of the contract.
- CCreate material-specific source lists for the contract item and set the Fix indicator.
- DCreate material-specific source lists for the supplier and set the Blocked indicator.
How the community answered
(67 responses)- A70% (47)
- B4% (3)
- C16% (11)
- D9% (6)
Community Discussion
No community discussion yet for this question.