SAP
C_TS452_2021 · Question #82
During reorder point planning, which time elements does the forward scheduling procedure take into account when calculating the availability date? There are 3 correct answers to this question.
The correct answer is A. Purchasing department processing time C. Goods receipt processing time D. Planned delivery time. See the full explanation below for the reasoning.
Question
During reorder point planning, which time elements does the forward scheduling procedure take into account when calculating the availability date? There are 3 correct answers to this question.
Options
- APurchasing department processing time
- BTotal shelf life
- CGoods receipt processing time
- DPlanned delivery time
- EGoods issue processing time
How the community answered
(64 responses)- A72% (46)
- B9% (6)
- E19% (12)
Community Discussion
No community discussion yet for this question.