Question

Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.

Options

  • ACarry out a lot-size calculation for every material with net requirements.
  • BPerform backward scheduling to determine the availability dates of purchase requisitions.
  • CCarry out a net requirement calculation for every material included in the planning run.
  • DFlag materials that have been subject to an activity relevant to MRP.