C_TS452_2021 · Question #80
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
The correct answer is A. Carry out a lot-size calculation for every material with net requirements. C. Carry out a net requirement calculation for every material included in the planning run. See the full explanation below for the reasoning.
Question
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
Options
- ACarry out a lot-size calculation for every material with net requirements.
- BPerform backward scheduling to determine the availability dates of purchase requisitions.
- CCarry out a net requirement calculation for every material included in the planning run.
- DFlag materials that have been subject to an activity relevant to MRP.
How the community answered
(18 responses)- A72% (13)
- B17% (3)
- D11% (2)