C_TS452_2021 · Question #41
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP…
The correct answer is C. Set a maximum quota quantity in the quota arrangement item for each supplier. D. Set a maximum lot size in the quota arrangement item and activate the 1x checkbox. See the full explanation below for the reasoning.
Question
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? Note: There are 2 correct answers to this question.
Options
- AAssign a rounding profile in the material master record of the planned material.
- BAssign the indicator for quota splitting to the lot-sizing procedure being used.
- CSet a maximum quota quantity in the quota arrangement item for each supplier.
- DSet a maximum lot size in the quota arrangement item and activate the 1x checkbox.
How the community answered
(46 responses)- A20% (9)
- B9% (4)
- C72% (33)