SAP
C_TS452_2021 · Question #40
You want to automatically create a scheduling agreement delivery schedule. How can this be accomplished? Please choose the correct answer.
The correct answer is B. Through material requirements planning (MRP). See the full explanation below for the reasoning.
Question
You want to automatically create a scheduling agreement delivery schedule. How can this be accomplished? Please choose the correct answer.
Options
- ABy running the program to generate scheduling agreement releases
- BThrough material requirements planning (MRP)
- CIn the background when creating a scheduling agreement
- DWith the release creation profile
How the community answered
(32 responses)- A9% (3)
- B69% (22)
- C19% (6)
- D3% (1)
Community Discussion