SAP
C_TS452_2021 · Question #42
You have agreed on a value contract with a supplier for packaging. The exact materials and their purchase prices are NOT specified until the release orders. Which item category must you use when…
The correct answer is B. M (Material unknown). See the full explanation below for the reasoning.
Question
You have agreed on a value contract with a supplier for packaging. The exact materials and their purchase prices are NOT specified until the release orders. Which item category must you use when creating the contract?
Options
- AW (Material group)
- BM (Material unknown)
- CB (Limit)
- DT (Text)
How the community answered
(21 responses)- A5% (1)
- B76% (16)
- C14% (3)
- D5% (1)
Community Discussion