SAP
C_TS450_1809 · Question #86
What do you need to consider when deciding whether to use stock transport orders for stock transfers between plants? Please choose the correct answer.
The correct answer is D. Stock transfers with stock transport orders require an account assignment. See the full explanation below for the reasoning.
Question
What do you need to consider when deciding whether to use stock transport orders for stock transfers between plants? Please choose the correct answer.
Options
- AStock transfers with transport orders are one step only
- BStock transfers with stock transport orders use the same calculation schema as
- CStock transfers with stock transport orders can be integrated with MRP
- DStock transfers with stock transport orders require an account assignment
How the community answered
(33 responses)- A18% (6)
- B6% (2)
- C3% (1)
- D73% (24)
Community Discussion
No community discussion yet for this question.