SAP
C_TS450_1809 · Question #43
Which release strategy control prevents a planning run from changing the quantity on a purchase requisition in SAP Materials Management? Please choose the correct answer.
The correct answer is C. Field selection key. See the full explanation below for the reasoning.
Question
Which release strategy control prevents a planning run from changing the quantity on a purchase requisition in SAP Materials Management? Please choose the correct answer.
Options
- AFixing indicator
- BRelease group
- CField selection key
- DRelease code
How the community answered
(31 responses)- A3% (1)
- B13% (4)
- C77% (24)
- D6% (2)