When the procurement process is without a material master in SAP Materials Management, which configuration element do you assign to the valuation class? Please choose the correct answer.
The correct answer is D. Material group. See the full explanation below for the reasoning.
Question
When the procurement process is without a material master in SAP Materials Management, which configuration element do you assign to the valuation class? Please choose the correct answer.
Options
- AMaterial type
- BItem category.
- CValuation area
- DMaterial group
How the community answered
(19 responses)- A16% (3)
- B5% (1)
- C5% (1)
- D74% (14)