For which of the following do you have to create MRP areas? Please choose the correct answer.
The correct answer is D. Storage location MRP. See the full explanation below for the reasoning.
Question
For which of the following do you have to create MRP areas? Please choose the correct answer.
Options
- AMRP run by vendor
- BMRP run with scope of planning
- CForecasting
- DStorage location MRP
How the community answered
(18 responses)- B11% (2)
- C6% (1)
- D83% (15)
Community Discussion
No community discussion yet for this question.