For which of the following do you have to create MRP areas? Please choose the correct answer.

The correct answer is D. Storage location MRP. See the full explanation below for the reasoning.

Question

For which of the following do you have to create MRP areas? Please choose the correct answer.

Options

  • AMRP run by vendor
  • BMRP run with scope of planning
  • CForecasting
  • DStorage location MRP

How the community answered

(18 responses)
  • B
    11% (2)
  • C
    6% (1)
  • D
    83% (15)