What purchasing master data has the highest priority during source determination in the material requirements planning run? Please choose the correct answer.

The correct answer is B. Quota arrangement. See the full explanation below for the reasoning.

Question

What purchasing master data has the highest priority during source determination in the material requirements planning run? Please choose the correct answer.

Options

  • AVendor master.
  • BQuota arrangement
  • CSource list
  • DInfo record

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    70% (21)
  • C
    20% (6)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full C_TS450_1809 Practice