SAP
C_TS450_1809 · Question #33
What purchasing master data has the highest priority during source determination in the material requirements planning run? Please choose the correct answer.
The correct answer is B. Quota arrangement. See the full explanation below for the reasoning.
Question
What purchasing master data has the highest priority during source determination in the material requirements planning run? Please choose the correct answer.
Options
- AVendor master.
- BQuota arrangement
- CSource list
- DInfo record
How the community answered
(30 responses)- A3% (1)
- B70% (21)
- C20% (6)
- D7% (2)
Community Discussion