SAP
C_TS450_1809 · Question #17
Which indicators do you set to allow evaluated receipt settlement in SAP Materials Management? There are 2 correct answers to this question.
The correct answer is A. Automatic settlement of goods received in the vendor B. Goods receipt based invoice verification in the purchase order. See the full explanation below for the reasoning.
Question
Which indicators do you set to allow evaluated receipt settlement in SAP Materials Management? There are 2 correct answers to this question.
Options
- AAutomatic settlement of goods received in the vendor
- BGoods receipt based invoice verification in the purchase order
- CAutomatic purchase order in the vendor master.
- DAuto-generation of purchase order at time of goods receipt in the movement type
How the community answered
(30 responses)- A73% (22)
- C20% (6)
- D7% (2)
Community Discussion
No community discussion yet for this question.