C_TS410_2504 · Question #52
What occurs when planning an internal project activity?
The correct answer is C. Purchase requisitions are generated. Project Planning and Activities: When planning activities for internal projects in SAP, resources, materials, and services required for the project are identified. Generating Purchase Requisitions: Automated Procurement: As part of the planning process, the system can…
Question
What occurs when planning an internal project activity?
Options
- ACosts are recorded
- BService is performed.
- CPurchase requisitions are generated.
- DResources are committed
How the community answered
(42 responses)- A5% (2)
- B10% (4)
- C71% (30)
- D14% (6)
Explanation
Project Planning and Activities: When planning activities for internal projects in SAP, resources, materials, and services required for the project are identified. Generating Purchase Requisitions: Automated Procurement: As part of the planning process, the system can automatically generate purchase requisitions for the materials and services needed for the project activities. Integration with Materials Management: These purchase requisitions can then be processed in the Materials Management (MM) module to procure the required resources.