C_TS410_2504 · Question #53
What document, when saved, creates a commitment for an internal order?
The correct answer is D. Purchase order. Commitments and Internal Orders: In SAP, a commitment represents an obligation to make a future payment. When a purchase order is issued, it creates a commitment against the associated internal order. Impact of Purchase Orders: Budget Control: The commitment from a purchase…
Question
What document, when saved, creates a commitment for an internal order?
Options
- AMaintenance order
- BProduction order
- CGoods receipt
- DPurchase order
How the community answered
(38 responses)- A8% (3)
- B3% (1)
- D89% (34)
Explanation
Commitments and Internal Orders: In SAP, a commitment represents an obligation to make a future payment. When a purchase order is issued, it creates a commitment against the associated internal order. Impact of Purchase Orders: Budget Control: The commitment from a purchase order helps in monitoring and controlling the budget for internal orders, ensuring financial discipline and planning. Financial Reporting: These commitments are important for financial reporting, providing insights into future financial obligations.
Topics
Community Discussion
No community discussion yet for this question.