C_TS410_2504 · Question #66
How can you post internal labor costs to a network activity? There are 2 correct answers to this question.
The correct answer is A. By activity allocation C. By confirmation. Internal Labor Costs on Network Activities (SAP Project System) Activity Allocation (A) allows you to directly allocate internal labor costs from a cost center to a network activity using activity types (e.g., labor hours at a defined rate), making it a primary method for…
Question
How can you post internal labor costs to a network activity? There are 2 correct answers to this question.
Options
- ABy activity allocation
- BBy distribution
- CBy confirmation
- DBy service entry sheet
How the community answered
(27 responses)- A78% (21)
- B7% (2)
- D15% (4)
Explanation
Internal Labor Costs on Network Activities (SAP Project System)
Activity Allocation (A) allows you to directly allocate internal labor costs from a cost center to a network activity using activity types (e.g., labor hours at a defined rate), making it a primary method for charging internal work. Confirmation (C) is correct because when you confirm a network activity, you record actual hours worked by internal resources, which automatically posts the corresponding labor costs to the activity based on the assigned activity type rates.
Distribution (B) is a Controlling tool that reallocates costs between cost centers using statistical keys - it does not post labor costs directly to network activities. Service Entry Sheet (D) is used to confirm receipt of external services from vendors against a purchase order, making it relevant for external (not internal) costs.
Memory tip: Think "AC for internal ACtion" - Activity allocation and Confirmation both involve internal resources performing work, which is exactly what internal labor represents. Anything involving vendors (service entry sheets) or cost center-to-cost center flows (distribution) is out of scope here.