C_TS410_2020 · Question #97
For what network activity can you plan capacities?
The correct answer is C. Service activity. See the full explanation below for the reasoning.
Question
For what network activity can you plan capacities?
Options
- AInternal activity
- BExternal activity
- CService activity
- DCost activity
How the community answered
(32 responses)- A3% (1)
- B13% (4)
- C78% (25)
- D6% (2)