C_TS410_2020 · Question #97

For what network activity can you plan capacities?

The correct answer is C. Service activity. See the full explanation below for the reasoning.

Question

For what network activity can you plan capacities?

Options

  • AInternal activity
  • BExternal activity
  • CService activity
  • DCost activity

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    78% (25)
  • D
    6% (2)