What is the hierarchical model of a project?
The correct answer is B. Work breakdown structure. See the full explanation below for the reasoning.
Question
What is the hierarchical model of a project?
Options
- ANetwork
- BWork breakdown structure
- CProject definition
- DTask list
How the community answered
(23 responses)- A13% (3)
- B78% (18)
- C4% (1)
- D4% (1)