SAP
C_TS410_2020 · Question #1
What can a planned order be converted to? There are two correct answers for this question.
The correct answer is B. A production order D. A purchase requisition. See the full explanation below for the reasoning.
Question
What can a planned order be converted to? There are two correct answers for this question.
Options
- AA planned independent requirement
- BA production order
- CA purchase order
- DA purchase requisition
How the community answered
(50 responses)- A6% (3)
- B80% (40)
- C14% (7)
Community Discussion
No community discussion yet for this question.