SAP
C_TS410_2020 · Question #2
You purchase raw materials with a purchase order against an internal order. During which process step are journal entries posted?
The correct answer is D. Post valuated goods receipt. See the full explanation below for the reasoning.
Question
You purchase raw materials with a purchase order against an internal order. During which process step are journal entries posted?
Options
- ASave purchase requisition
- BRelease purchase order
- CCalculate the payment method
- DPost valuated goods receipt
How the community answered
(56 responses)- A2% (1)
- B7% (4)
- C11% (6)
- D80% (45)