You need stock materials to complete your maintenance process. At what steps can a material reservation be created? There are two correct answers for this question
The correct answer is C. Release an order D. Technically complete an order. See the full explanation below for the reasoning.
Question
You need stock materials to complete your maintenance process. At what steps can a material reservation be created? There are two correct answers for this question
Options
- ASave an order
- BSettle an order
- CRelease an order
- DTechnically complete an order
How the community answered
(23 responses)- A17% (4)
- B9% (2)
- C74% (17)