Which processes can be automatically performed when you post an order confirmation for a production order? There are three correct answers for this question

The correct answer is A. Goods receipt D. Variance calculation E. Order settlement. See the full explanation below for the reasoning.

Question

Which processes can be automatically performed when you post an order confirmation for a production order? There are three correct answers for this question

Options

  • AGoods receipt
  • BGoods issue
  • CPost actual costs
  • DVariance calculation
  • EOrder settlement