What can a successful MRP run create?
The correct answer is A. Dependent requirements. See the full explanation below for the reasoning.
Question
What can a successful MRP run create?
Options
- ADependent requirements
- BReservations
- CPurchase orders
- DPlanned independent requirements
How the community answered
(60 responses)- A77% (46)
- B7% (4)
- C13% (8)
- D3% (2)
Community Discussion