nerdexam
SAP

C_TS410_2020 · Question #72

How can you post internal labor costs to a network activity? There are two correct answers for this question

The correct answer is B. Activity allocation C. Confirmation. See the full explanation below for the reasoning.

Question

How can you post internal labor costs to a network activity? There are two correct answers for this question

Options

  • ADistribution
  • BActivity allocation
  • CConfirmation
  • DService entry sheet

How the community answered

(48 responses)
  • A
    19% (9)
  • B
    73% (35)
  • D
    8% (4)

Community Discussion

No community discussion yet for this question.