C_TS410_2020 · Question #68
What MRP control parameter defines the scope of a planning run?
The correct answer is D. Processing key. See the full explanation below for the reasoning.
Question
What MRP control parameter defines the scope of a planning run?
Options
- AProcurement type
- BPlanning mode
- CLot size
- DProcessing key
How the community answered
(37 responses)- A8% (3)
- B16% (6)
- C3% (1)
- D73% (27)