Which of the following sequences of the source-to-pay process steps are correct? Please choose the correct answer.

The correct answer is C. 1. Determination of requirements. See the full explanation below for the reasoning.

Question

Which of the following sequences of the source-to-pay process steps are correct? Please choose the correct answer.

Options

  • A
    1. Determination of requirements
  • B
    1. Vendor selection
  • C
    1. Determination of requirements
  • D
    1. Source of supply determination

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    73% (19)
  • D
    8% (2)