What function compares assigned funds to the budget of a work breakdown structures (WBS) element?

The correct answer is D. Settlement. See the full explanation below for the reasoning.

Question

What function compares assigned funds to the budget of a work breakdown structures (WBS) element?

Options

  • ACost forecast
  • BResults analysis
  • CAvailability control
  • DSettlement

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    81% (30)