C_TS410_2020 · Question #28
What function compares assigned funds to the budget of a work breakdown structures (WBS) element?
The correct answer is D. Settlement. See the full explanation below for the reasoning.
Question
What function compares assigned funds to the budget of a work breakdown structures (WBS) element?
Options
- ACost forecast
- BResults analysis
- CAvailability control
- DSettlement
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C11% (4)
- D81% (30)