SAP
C_TS410_2020 · Question #25
How do you use the result of a released standard cost estimate? There are three correct answers for this question
The correct answer is C. To calculate the price of an activity type D. To update the current standard price in the material master record E. To calculate the plan costs in a production order. See the full explanation below for the reasoning.
Question
How do you use the result of a released standard cost estimate? There are three correct answers for this question
Options
- ATo determine the base costs used to calculate overhead
- BTo determine a material sales price in Sales and Distribution
- CTo calculate the price of an activity type
- DTo update the current standard price in the material master record
- ETo calculate the plan costs in a production order
How the community answered
(46 responses)- A17% (8)
- B11% (5)
- C72% (33)