In a project, what is linked via relationships?

The correct answer is D. Activities. See the full explanation below for the reasoning.

Question

In a project, what is linked via relationships?

Options

  • AWork breakdown structure elements
  • BNetworks
  • CProject definitions
  • DActivities

How the community answered

(60 responses)
  • A
    3% (2)
  • B
    13% (8)
  • C
    7% (4)
  • D
    77% (46)