What master data in the activity type is used to post an activity allocation?
The correct answer is A. Secondary cost element. See the full explanation below for the reasoning.
Question
What master data in the activity type is used to post an activity allocation?
Options
- ASecondary cost element
- BBalance sheet account
- CPrimary cost element
- DNon-operating expense
How the community answered
(19 responses)- A79% (15)
- B5% (1)
- C5% (1)
- D11% (2)