C_TS410_1809 · Question #59

What assigns actual costs to a project?

The correct answer is B. Posting a vendor's invoice. See the full explanation below for the reasoning.

Question

What assigns actual costs to a project?

Options

  • AProcessing a cost forecast
  • BPosting a vendor's invoice
  • CSaving a purchase order
  • DCalculating project interest

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    82% (36)
  • C
    11% (5)
  • D
    5% (2)