What can you record during overall completion confirmation of a maintenance order?
The correct answer is B. Notification completion. See the full explanation below for the reasoning.
Question
What can you record during overall completion confirmation of a maintenance order?
Options
- AMeasurements
- BNotification completion
- CSerial numbers
- DPlanned time
How the community answered
(25 responses)- A4% (1)
- B76% (19)
- C8% (2)
- D12% (3)