C_TS410_1809 · Question #41
What MRP control parameter defines the scope of a planning run?
The correct answer is D. Processing key. See the full explanation below for the reasoning.
Question
What MRP control parameter defines the scope of a planning run?
Options
- AProcurement type
- BPlanning mode
- CLot size
- DProcessing key
How the community answered
(18 responses)- A6% (1)
- B17% (3)
- C6% (1)
- D72% (13)