What is the hierarchical model of a project?
The correct answer is B. Work breakdown structure. See the full explanation below for the reasoning.
Question
What is the hierarchical model of a project?
Options
- ANetwork
- BWork breakdown structure
- CProject definition
- DTask list
How the community answered
(29 responses)- A7% (2)
- B72% (21)
- C17% (5)
- D3% (1)