SAP
C_TPLM30_66 · Question #94
Your customer has several plants. How do you set up the maintenance organizational structure to implement centralized maintenance planning?
The correct answer is D. Define a planning plant and assign the maintenance plants to this planning plant in Customizing. See the full explanation below for the reasoning.
Question
Your customer has several plants. How do you set up the maintenance organizational structure to implement centralized maintenance planning?
Options
- AAssign all your work centers to one of your central planning plants.
- BDefine a plant and assign it to a company code.
- CAssign all your work centers to one of your maintenance plants.
- DDefine a planning plant and assign the maintenance plants to this planning plant in Customizing.
How the community answered
(22 responses)- A14% (3)
- B9% (2)
- C5% (1)
- D73% (16)
Community Discussion
No community discussion yet for this question.