C_TPLM30_66 · Question #67
Which of the following combinations must you use to create a single-cycle maintenance plan for an external service?
The correct answer is B. A framework order and a maintenance order for settlement. See the full explanation below for the reasoning.
Question
Which of the following combinations must you use to create a single-cycle maintenance plan for an external service?
Options
- AA maintenance order for settlement and an outline agreement
- BA framework order and a maintenance order for settlement
- CA framework order and a subcontract purchase order
- DA subcontract purchase order and an outline agreement
How the community answered
(35 responses)- A17% (6)
- B71% (25)
- C9% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.