Your customer uses the dynamic availability check for stock material. Where does the system check material availability for an operation?

The correct answer is B. Only in the plant where the material has been reserved. See the full explanation below for the reasoning.

Question

Your customer uses the dynamic availability check for stock material. Where does the system check material availability for an operation?

Options

  • AIn all plants where material inventory exists
  • BOnly in the plant where the material has been reserved
  • COnly in the plant where the material is flagged with the special stock indicator for maintenance
  • DIn all plants where the material is managed with serial numbers

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    74% (23)
  • C
    13% (4)
  • D
    3% (1)