nerdexam
SAP

C_TPLM30_66 · Question #49

What happens when you set the system status in a maintenance order to technically completed (TECO)? (Choose two)

The correct answer is A. The system sets a deletion indicator for outstanding reservations. B. The system sets a deletion indicator for outstanding purchase requisitions. See the full explanation below for the reasoning.

Question

What happens when you set the system status in a maintenance order to technically completed (TECO)? (Choose two)

Options

  • AThe system sets a deletion indicator for outstanding reservations.
  • BThe system sets a deletion indicator for outstanding purchase requisitions.
  • CThe system posts costs to the target account assignment.
  • DThe system sets a deletion indicator for purchase orders assigned to the maintenance order.

How the community answered

(28 responses)
  • A
    82% (23)
  • C
    7% (2)
  • D
    11% (3)

Community Discussion

No community discussion yet for this question.

Full C_TPLM30_66 Practice