nerdexam
SAP

C_TPLM30_66 · Question #34

What does the scheduling period determine in the maintenance plan scheduling parameters?

The correct answer is B. The duration for which the system generates planned or call dates during scheduling. See the full explanation below for the reasoning.

Question

What does the scheduling period determine in the maintenance plan scheduling parameters?

Options

  • AThe duration for which the system generates maintenance orders immediately
  • BThe duration for which the system generates planned or call dates during scheduling
  • CThe duration for which the system generates maintenance notifications immediately
  • DThe validity period of the maintenance plan

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    78% (25)
  • C
    13% (4)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full C_TPLM30_66 Practice