C_TPLM30_66 · Question #17
What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)
The correct answer is C. The numeric value for Work in the order operation must be greater than 0. D. The operation must have a control key with the Determine Capacity Requirements indicator set. See the full explanation below for the reasoning.
Question
What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)
Options
- AThe performing work center must have available capacity data.
- BThe performing work center must have a control key with the Determine Capacity Requirements
- CThe numeric value for Work in the order operation must be greater than 0.
- DThe operation must have a control key with the Determine Capacity Requirements indicator set.
How the community answered
(30 responses)- A10% (3)
- B20% (6)
- C70% (21)
Community Discussion