In order costing configuration, for what is the allocation structure used?

The correct answer is D. To determine the settlement receiving elements for costs debited to the order. See the full explanation below for the reasoning.

Question

In order costing configuration, for what is the allocation structure used?

Options

  • ATo provide a method of consolidating costs in the Plant Maintenance Information System
  • BTo allocate costs to a hierarchy of maintenance technical objects
  • CTo determine the cost elements that are allowed in the plant maintenance order
  • DTo determine the settlement receiving elements for costs debited to the order

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    8% (2)
  • D
    77% (20)