A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category. Where do the material costs appear in the value…

The correct answer is C. In the unassigned value category. See the full explanation below for the reasoning.

Question

A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category. Where do the material costs appear in the value categories for the order?

Options

  • AIn the overhead value category
  • BIn a new, automatically created value category
  • CIn the unassigned value category
  • DIn the internal activity value category

How the community answered

(52 responses)
  • A
    13% (7)
  • B
    8% (4)
  • C
    75% (39)
  • D
    4% (2)

Community Discussion