A maintenance work order has external processing. The planning plant and maintenance plant have different addresses. A purchase requisition is generated from a maintenance order. With standard…
The correct answer is C. Planning plant. See the full explanation below for the reasoning.
Question
A maintenance work order has external processing. The planning plant and maintenance plant have different addresses. A purchase requisition is generated from a maintenance order. With standard delivered SAP Customizing, which address is the default delivery address in the purchase requisition?
Options
- AWork center
- BStorage location
- CPlanning plant
- DMaintenance plant
How the community answered
(48 responses)- A4% (2)
- B8% (4)
- C71% (34)
- D17% (8)