nerdexam
SAP

C_TPLM30_65 · Question #4

What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)

The correct answer is C. The numeric value for Work in the order operation must be greater than 0. D. The operation must have a control key with the Determine Capacity Requirements indicator set. See the full explanation below for the reasoning.

Question

What are the prerequisites for creating a capacity requirement in a maintenance order operation? (Choose two)

Options

  • AThe performing work center must have available capacity data.
  • BThe performing work center must have a control key with the Determine Capacity Requirements indicator set.
  • CThe numeric value for Work in the order operation must be greater than 0.
  • DThe operation must have a control key with the Determine Capacity Requirements indicator set.

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    6% (2)
  • C
    84% (26)

Community Discussion

No community discussion yet for this question.

Full C_TPLM30_65 Practice